The first unit of the Rooppur Nuclear Power Plant experimentally supplied 350 megawatts of electricity to the national grid on Tuesday, marking the country's first-ever grid injection from a nuclear power plant.
The electricity supply began at 3:16pm in the presence of science and technology minister Faqir Mahbub Anam at the plant in Ishwardi, Pabna, according to a press release issued by the Bangladesh Atomic Energy Commission.
The initial grid connection will continue for around eight to ten hours to assess the performance and stability of the plant's turbine, generator and integrated grid operation systems, the release said.
The plant will then be disconnected from the national grid for around 28 hours to conduct further technical tests. It will subsequently be reconnected for another four to six hours to complete additional technical and operational assessments.
The performance of different plant systems, the turbine and generator, and their coordination with the national grid will be closely monitored during each stage of testing.
Following satisfactory results, the plant will require approval from the Bangladesh Atomic Energy Regulatory Authority to proceed with the next phase of trial operation, the commission said.
Under the agreement with the Russian contractor, the first unit will undergo a 10-month trial operation before it can begin commercial electricity supply at full capacity.
Each of the plant’s two units has a generation capacity of 1,200MW, giving the facility a combined capacity of 2,400MW.
The Rooppur project is expected to contribute to meeting the country’s growing electricity demand and strengthening energy security.